Throwback to our first Major project – Kitchen Remodel part 2
- Home
- /
- Throwback to our first Major project – Kitchen Remodel part 2
Some product links are affiliate links, which means if you buy something, we may receive a small commission at no additional cost to you.
Last updated on July 3, 2020
Week 2
The first week of demolition went pretty good with only a few hiccups but when we got to the underlayment and subfloor this last week it has been miserable. The subfloor definitely needed replacing especially after we pried the underlayment up. It took a week to lay the subfloor mainly because we had to be careful with the open sections. We have learned a lot about the different ways to construct a house. For instance, some builders use rafters as duct work for return air. In 1962 the standard was nailing your 1/2" subfloor, now they recommend screwing at least 5/8". Knotted wood was not preferred but now plywood is chalked full of them.| He found a gap to spy into the basement. |
Week 3
The following week was installing can lighting. Started out only going to have 6 lights and ended up with 8. The recessed lighting helps give a taller ceiling effect, with such a long narrow room it needed it. This is the week our new fridge arrived :) It may be sitting in our living room waiting to be plugged in but we all can't wait to get it in the kitchen.| Late night of wiring lights |
| Lights in and drywall down |
| Now the kitchen is insulated! |
Week 4
Week 4 was putting up the drywall. Very time consuming but really brought the room together. Mudded and sanded many times, painted the ceiling and walls. Very exciting since much of the week was consumed with graduations, showing property, writing offers, work, and kids.| We had great little helpers |
| Painted, all but 1 wall luckily it will be covered with cabinets and backsplash. Next time 2 gallons of paint needed. |
Weeks 5 and 6
Week 5 has been hard, stormy weather daily which is not ideal for mixing thinset let alone carrying in the hardyboard. Here is a sneak preview of what we did for the rest of week 5 and beginning of 6: Cabinets arrived on May 21! A day of excitement especially for the boys who made forts while we installed the contents. Until next time... Curious about all the tools and gear we use? Full list Here 📷 Follow us on Instagram 👍 Join us of FacebookConnect with Top Homeowner on Social Media
📷 Follow on Instagram: https://www.instagram.com/tophomeowner/
👍 Join us of Facebook: https://www.facebook.com/TopHomeowner/
🐦 Tweet us on Twitter: https://twitter.com/tophomeowner
❓ QUESTIONS — Have a question about Home Maintenance, Home Repair, Home Related Products, Organization, or Anything Else? Post a comment!
📢 Subscribe to Top Homeowner YouTube Channel Here: https://geni.us/tophomeowner